Salient
Features
Sunkoshi HPP is a PRoR project.
Full capacity : 10.05 MW ( 3 units generating
3.35 MW each) at 6.3 KV
Construction start date: December of 1968
Construction complete date: January 1972
Project cost : 11 Crore NRs.
Well, you can buy 223 bullet motor cycle with
that money.
The project was constructed as bilateral
project with funding provided from then Chinese Government and then His
majesty’s Government of Nepal.
Sunkoshi Barrage
Sunkoshi barrage with hoisting room above
Canal
The average discharge in Sunkoshi River:
88 cu.sec.
There is a canal constructed with discharge
capacity of 40 cu.sec
There are two canals:
1.Main canal (2793m)
2.Side canal
Under normal condition, main canal operates.
However, whenever the main canal is not
functioning due
to the dredging work in settling basin, side
can takes its
place. At present side canal is functioning.
Settling
Basin
Hopper type settling basin is present in main
canal .It is a continuous flushing system.
Hopper type Settling basin Settling basin filled with sediment
Trash
Rack
Trash rack is present in both
Main and Side canals’ entrance.
It functions in checking the entry larger
sediments and the floating debris in the river
Peaking
Pond
Size of Preaking pond : 67000 cu m
It is used for satisfying the peaking demand
of one and half day.
It is not functional at present.
Forebay
Size of Forebay is 18000 cu.m
It is energy dissipating structure.
It protects the 3 Penstocks below.
It is also provided with trash rack.
Penstock
There are 3 Penstocks.
Its length is 87m each and the diameter is
2.4 m each.
These are extremely expensive.
At present only two are runing, due to the misphap
that occurred in upstream of the barrage.
Turbine
The are 3 turbines receiving flow form 3 penstocks.
Turbine type:
Reaction turbine- Francis turbine.
Which is the desirabe turbine for medium head
of 30.5m
The speed of rotation( optimum)= 300rpm.
Other
features
- 8 years earlier : Manual Cotrol System.
-At present :Electronic Control System.
-Cooling system:
-Natural air cooling-Air forced cooling
-Water forced cooling
-Oil cooling (90 liter of oil is used)
Plan of Sunkoshi Hydropower Project showing its headworks